Timeline |
Task
|
Date |
|
SEVA meeting |
1/11/05 |
|
Safety meeting with Russ Noe |
1/11/05 |
|
Design Proposal, Safety Plan and Presentation |
1/13/05 |
|
Contact information for EV maintenance |
1/13/05 |
|
Possible battery choices |
1/14/05 |
|
Battery choice evaluation |
1/23/05 |
|
Battery selection |
1/25/05 |
|
Determine battery configuration |
2/1/05 |
|
Midterm report |
2/10/05 |
|
Finite element analysis (FEA) of battery case |
2/16/05 |
|
Determine case material from results of FEA |
2/18/05 |
|
Complete budget breakdown for battery purchase |
3/3/05 |
|
Complete budget breakdown and suppliers list for
manufacture of the battery case |
3/7/05 |
|
Determine manufacturing method for case |
3/7/05 |
|
Complete website |
3/14/05 |
|
This is just a quick glance at some of the major points in our
project. The complete timeline can be found in the final report in
the embodiment design.
|
Timeline This is what our quarterly timeline ended up looking like. Our
initial timeline can be found in the design proposal in the archive
section. As we continued with the work throughout the quarter, we
realized that a lot of the goals that we had set in out original
timeline were undoable, and our final timeline reflects those
changes. We feel that it would require more time and money
to successfully design the case as we originally intended. |